Jack!

We did jack this weekend.

It took most of Saturday to get the supports and bracing in place. I added diagonal bracing below, to try to stabilize everything as much as possible. When the back room is cut off the house, the only thing stopping it from toppling over will be these braces. I wore my hard hat so that I didn’t keep hitting my head. Looks more professional, too!

Using a reciprocating saw, I cut all the way round, through the nails that held the laundry room onto the house, completely separating it from the house. We also disconnected piping (well, most of it – see later) and other things that held the floor to the house.

Above left you can see the step (red) between the kitchen and the laundry room.

Once we started jacking, Janeen ran outside and took a photo (above right). You can see a gap under the framing that is going up with the floor, and the wall below.

Above left, there’s about six inches between the floor and the wall below. Above right, this is half way there.

While we were pumping the jack, there were all sorts of creaking noises. Sometimes there was the sound of splitting wood, or sudden cracks. After one noise, I went outside, and found that I’d forgotten to disconnect the sewer pipe from the wall, so it was being lifted up with the room and had separated at a joint. I had to disconnect it, and carefully slide it back down into place (while up on a ladder, leaning on the room sitting on temporary supports – above left).

Above right, you can see light shining through a gap between the house and the laundry room. The whole thing would tilt sideways as we jacked up one side. Then it would tilt back when we jacked the other side. I didn’t realize it would tilt around this much, and am really glad I put in the bracing. It’s quite scary being underneath all this with the jack.

Janeen kept calling it ‘reverse Jenga’. I have one 20-ton jack but have six support points to lift the room at. We put the jack onto one of the supports, and pumped it until it lifted that side about 1 1/2″. Then I slipped a couple of 2×4’s into the gap, and let the pressure off the jack. Then we moved it to the next location. It took all day.

Above right, here’s the gap after getting the floor to the right level.

Above left: Flush! There’s no more step down. Above right, the whole room was moving around while we jacked it up. At one point, I noticed that as I was jacking, the room was moving sideways. A piece of wood had got stuck, and was levering the whole room sideways about 1/4 inch before I stopped. To get it back into place, I screwed a block of wood to the floor joists of the laundry room, and a block to the side of the house. Then I tightened a clamp between the two pieces of wood to pull it over. It worked!

Above left, here’s a nice (scary) pile of wood supporting the laundry room. Above right, at this side of the room, it raised up about a foot, because the floor of the laundry room (in addition to the step), sloped away from the building.

It’s been a funny winter. Actually, I think there was none. It only rained two or three times. And now it’s spring. The daffodil, crocus and iris bulbs that we planted around the tree are popping up. And the peach tree is coming into blossom already. Janeen took a photo of a couple of sprigs we brought in and put into water.

Head Banger

Besides working my tail off on paid work, I’ve been plodding forward on the house, preparing to raise up the floor of the laundry room.

The floor framing in this space was done without much help from engineering. It also did not leave much head room in the space below (I can’t remember how many times I’ve hit my head — probably once a day — working on this.) In place of the two undersized beams that span across, I’m replacing with a slightly deeper beam, but I’m setting the top of it flush with the top of the joists. I have to cut all the joists to get it in. Janeen caught a photo of me after I’d cut a couple of the joists. No going back now.

Janeen spent most of last weekend pulling nails out of old pieces of wood. I’ve got such a pile now, I need to figure out a project to use it all on.

Using some old wood, we made some support contraptions to fit the jack, and support the floor while we jack it up. It was a bit tricky getting them in place: I managed to break two windows simultaneously when the post fell over and smashed them (left). Right now, I’ve got the beam in the middle, and have put load onto the first two support posts. How do I know that they are carrying the weight (see below)?

This is a photo looking at one of the old beams (above left).

Two things: One, there’s now a gap under it, because all the weight is on the new beam. But the second is the troubling thing in earthquake country: When the previous person did this, they just sat the beam on top of loose blocks of wood. That’s fine until the building starts shaking around: Then, the blocks would just slide out, and the whole room would have come down! Speaking of earthquakes, I also added more plywood on the wall upstairs. The wiring for the light switch is just temporary!

Next, I have to get the outside walls supported, and disconnect this room from the building. Then I can start jacking…

happy birthday misha!

bella and arwen wish you a warm and fuzzy happy birthday and ask, “when is uncle misha coming to see us?”

bella would like to sit on your lap some more.

we hope your day is full of loved ones…

…and smiles.

…and not too much work.

we miss you and hope turning 40 is FUN!

lots of love from mathew, janeen, arwen and bella xoxo